Skip to content
Home / Case studies / CS · 04 — A41 / Park Lane
CS · 04 — MAY 2025

A bus corridor stayed live through a four-week carriageway repair. We finished on day three.

Client
LB Westminster
Contractor
Meridian TM
Site
A41 · Park Lane
Units deployed
2 × M1
Programme
3 days (28 planned)
CARRIAGEWAY REPAIR · 240 MM1 · AM1 · BBUS CORRIDOR — UNAFFECTEDSHUTTLE LANE — VEHICLE-ACTUATED270 M ZONE · CYCLE 84 S
FIG · 04.1 — SITE LAYOUT, A41 PARK LANE · MAY 2025SCALE — INDICATIVE
−25days
Vs. 28-day baseline
2
M1 units deployed
100%
Bus corridor uptime
£0
Diversion plan cost
§ 01 · Brief

The brief.

A 240-metre stretch of the A41 northbound carriageway needed full-depth repair. The default plan ran a four-week diversion through a residential network. Bus services along the corridor would have rerouted around it — TfL had pre-flagged the disruption.

Westminster’s traffic team asked: could a portable shuttle hold the corridor live for buses, with a single closed lane for general traffic, while the work was done in place?

It is the kind of question fixed signal infrastructure cannot answer — but it is exactly the kind of question portable, instrumented kit was designed for.

§ 02 · Approach

Two M1s, vehicle-actuated, telemetry to the council.

Two M1 units in shuttle mode, vehicle-actuated, with cycle timings tuned to the corridor’s morning and evening profiles. Telemetry was shared with Westminster’s control room from the moment of commissioning.

Through the work window, anyone with access could see the unit state — head colour, cycle in flight, queue presence — at a 10-second cadence. When a contractor lifted the eastern unit on day 2 to relocate by 6 metres, Westminster saw the tilt event before the radio ack came through.

That visibility removed the need for a daily check-in call. The council’s operations team and the contractor were looking at the same record.

“The audit trail removed an entire class of dispute from our procurement reviews. We just stopped having those conversations.”

— TRAFFIC OPS LEAD · LB WESTMINSTER · APR 2025

03 · Timeline

DAY −2
19 MAY · 14:00
Site walk + commissioning. Two M1 units placed, surveyed, and registered against job ticket A41-PL-0524. Telemetry confirmed at council control.
DAY 0
21 MAY · 06:00
Closure live. Cycle 84 s, vehicle-actuated. First bus through northbound at 06:14, on schedule.
DAY 1
22 MAY · 11:30
Carriageway profile complete; surfacing crew on site by 12:00.
DAY 2
23 MAY · 09:42
Tilt event flagged on east unit (relocation by contractor, 6 m). Auto-paused; resumed cycle within 4 min.
DAY 3
24 MAY · 17:00
Carriageway reopened. Closure removed at 17:00. Units recovered to depot 23:30.
DAY +5
29 MAY
Audit pack issued: 86,400 telemetry events, full event log, six-page summary signed by both parties.

04 · Related cases

CS · 03 · MAR 2025

Wembley utility cut-in — single weekend window

Twelve units, three crews. £42k saved against quoted programme.

CS · 02 · JAN 2025

Camden emergency main repair — 90 minutes on site

Out-of-hours dispatch. Signal commissioned ahead of crew.

CS · 01 · SEP 2024

M25 J7 contraflow — eight-week programme

Four-lane contraflow. 99.97% uptime; zero incidents.

Have a site that needs an answer like this?