Skip to content
Home / Case studies / CS · 01 — M25 J7 contraflow
CS · 01 — SEP 2024

An eight-week motorway contraflow held 99.97% uptime, with no signal-related incidents.

Client
National Highways
Contractor
Brennan Civils
Site
M25 J7 (Reigate)
Units deployed
4 × M1
Programme
8 weeks
CARRIAGEWAY UNDER REPAIR · LANES 1-2CONTRAFLOW · LANES 3-4NORMAL FLOW · LANES 5-6M1·AM1·BM1·CM1·D3.2 KM CONTRAFLOWFOUR UNITS · TAPER ENDS · CYCLE 120 S
FIG · 01.1 — SITE LAYOUT, M25 J7 · SEP 2024SCALE — INDICATIVE
99.97%
Signal uptime, 8 weeks
0
Signal-related incidents
4
M1 units deployed
3.2km
Contraflow length
§ 01 · Brief

The brief.

National Highways needed an eight-week contraflow on the M25 J7 anticlockwise to allow full-depth resurfacing of the inside two lanes. The default plan called for fixed 200-mm signals on temporary gantries, with portable kit as backup.

The contractor asked whether four portable units could replace the gantries entirely, on the grounds that the unit cost was lower and the audit trail was richer. National Highways’ incident review team had reservations — the category had a reputation for failing on long-duration motorway work.

Ardent agreed to a stepped commissioning: two units for the first week, four for the remainder, with the contractor’s choice to revert at any point.

§ 02 · Approach

Four units, paired, with hot-spare battery rotation.

Two units at the contraflow taper, two at the merge, all on 120-second cycles with vehicle actuation disabled — on the M25 the queue is the steady state, not the exception. Battery packs rotated on a 72-hour cadence; depot van picked up depleted packs nightly.

Telemetry was ported into National Highways’ incident dashboard via the read-only API. The duty incident officer could see all four units at a glance, with cycle state, battery level, and tilt history. The unit nearest the merge was paired with a hot spare in the central reservation, on standby for swap.

The hot spare was not used. It was visible in the audit trail, which mattered more than the swap itself.

“Eight weeks, four units, zero radio calls about signal failures. We will be specifying instrumented portable as standard for next year’s programme.”

— INCIDENT REVIEW LEAD · NATIONAL HIGHWAYS · NOV 2024

03 · Timeline

WK −1
02 SEP
Site survey + commissioning trial. Two units placed at taper, telemetry confirmed at NH ROC.
WK 0
09 SEP · 22:00
Contraflow live. Cycle 120 s, fixed timing. First HGV through anticlockwise at 22:14.
WK 1
16 SEP
Stepped to four units; merge pair commissioned, hot spare placed in central reservation.
WK 3
30 SEP · 04:12
Battery thermal event flagged on M1·C (38°C ambient). Auto-throttled cycle; hot spare rotated in 06:00, M1·C returned to depot for inspection.
WK 5
14 OCT
Mid-programme review. NH incident team confirmed 100% uptime to date; contractor opted not to revert.
WK 7
28 OCT · 03:42
Radio fallback engaged on M1·A (4G outage 18 min). LoRaWAN held telemetry; cycle uninterrupted.
WK 8
04 NOV · 05:00
Contraflow removed. Carriageway reopened on schedule. Units recovered to depot 11:30.
WK +2
18 NOV
Audit pack issued: 4.84M telemetry events, 12-page summary, signed by NH and Brennan Civils.

04 · Related cases

CS · 04 · MAY 2025

A41 / Park Lane — bus corridor stayed live

Two units, three days. £0 diversion plan cost.

CS · 03 · MAR 2025

Wembley utility cut-in — single weekend window

Twelve units, three crews. £42k saved against quoted programme.

CS · 02 · JAN 2025

Camden emergency main repair — 90 minutes on site

Out-of-hours dispatch. Signal commissioned ahead of crew.

Long-duration programme on the horizon?